Datuk Seri Mohamed Khaled Nordin says Maharaja Lela-class ship now undergoing equipment, tool installation before harbour trials in Dec, followed by sea trials
The Public Accounts Committee expressed concern over the 86-day delay in the construction of littoral combat ships. This comes after PAC received a follow-up report from the Defence Ministry.
The additional RM2 billion allocation to complete the five littoral combat ships (LCS) is to be used for the project’s non-recurring costs and is not due to cost overruns as a result of delays, Defence Minister Datuk Seri Mohamad Hasan assured.
The Public Accounts Committee found that the implementation of the mobilisation plan for the littoral combat ship project has not yet reached a significant level.
The Malaysian Muslim Restaurant Owners’ Association (Presma) will proceed with suing a TikTok user for making defamatory claims about food preparation and cleanliness at mamak restaurants.
Langkah Dubai, a move by the opposition to topple Prime Minister Datuk Seri Anwar Ibrahim’s administration, is allegedly masterminded by former prime minister Tun Dr Mahathir Mohamad and his right-hand man Tun Daim Zainuddin.