Rehda Malaysia lauds Federal Court ruling on property delivery period

Association president Datuk Ho Hon Sang says decision provides significant reprieve for industry as it confirms no retroactive effect

12:38 PM MYT

 

KUALA LUMPUR – The Real Estate and Housing Developers’ Association (Rehda) Malaysia applauded the Federal Court’s decision yesterday regarding Prema Bonanza Sdn Bhd and Sri Damansara Sdn Bhd, which addressed and resolved uncertainties surrounding property delivery schedules. 

Rehda Malaysia president Datuk Ho Hon Sang said the recent ruling provides a significant reprieve for the industry. 

The ruling confirms that Regulation 11(3), which was found to be ultra vires in the Ang Ming Lee & Ors v the Housing and Local Government Ministry & Anor case in 2020, will not have a retroactive effect, thereby preventing possible negative impacts on the industry. 

Another legal principle affirmed by the Federal Court, according to the statement, is the Second Actor Theory.  

This principle holds that the second actor, who relied on the first actor’s actions even if they were unlawful, should not be penalised for executing the letter to grant an extension by the controller. 

“As an association representing housing developers in Malaysia, we have continuously encouraged member and non-member developers to adhere to the law, both at the state and federal levels.  

“These two developers have fulfilled their obligations according to the terms of the contract in the development of their respective projects, and the ruling today is a recognition of that.  

“We would also like to reiterate that we are not in favour of unnecessary extension of time unless, for very valid reasons, developers must honour the terms in the contracted sales to deliver within the time allowed by the law.  

“However, we are cognisant that despite our efforts, there may be a few developers who fail to comply with the rules and regulations properly, and we strongly urge them to change and undertake developments more responsibly.  

“We need to ensure proper delivery of houses for the rakyat, as homebuyers will not be only victims should you fail to do so, but also the nation,” he added. 

He also reiterated that Rehda will continue encouraging its members to uphold their role in nation-building by providing quality, affordable homes for the rakyat in a timely and sustainable manner. 

Yesterday, the Federal Court rejected claims by home buyers seeking damages for late property delivery, aiming to prevent purchasers from unjustly enriching themselves. 

The case involves buyers who purchased homes in 2012 with contracts stipulating a 54-month delivery period for their high-rise properties. 

However, the Housing Development (Control and Licensing) Regulations 1989 mandate a delivery time of 24 months for landed homes and 36 months for strata properties.  

The Controller of Housing, however, granted developer Prema Bonanza Sdn Bhd an extension of time.  

On November 26, 2019, the Federal Court ruled in the case of Ang Ming Lee & Anor v the Housing and Local Government Ministry that the minister could not empower the Controller of Housing to grant developers extensions for property delivery. – July 27, 2024 

Topics

 

Popular

Influencer who recited Quran at Batu Caves accused of sexual misconduct in Netherlands

Abdellatif Ouisa has targeted recently converted, underage Muslim women, alleges Dutch publication

Ramli Ngah Talib next Governor of Penang?

Former Perak Mentri Besar expected to succeed Tun Ahmad Fuzi Abdul Razak in May, with the latter only having served one term

FashionValet a loss-making entity before and after Khazanah, PNB’s RM47 mil investment

GLICs bought stakes in 2018, company records show total RM103.3 million losses after tax from 2017 to 2022

Related